22.05.2019


The team of thecontract on restoration in Monrepo Park is extended from 25 months to 35 months (until September 2020)

The main reasons are:

- long-term receipt of permits including the re-receipt of the environmental impact assessment for the project (the initial project conclusion ended in December 2016)

 - making changes to the project documentation, which, if necessary, were agreed with the Committee on Culture of the Leningrad Region: clarifying the configuration of the tracks, replacing stabilized coverage on the designed route for people with limited mobility, increasing the amount of work on cleaning coastal waters (since cane), multiple outcrops of rocks during the laying of external networks, etc.